Which statement correctly reflects the outriggers permit requirement?

Prepare for the Special Riggers Test. Study with flashcards and multiple-choice questions, complete with hints and explanations. Ace your exam!

Multiple Choice

Which statement correctly reflects the outriggers permit requirement?

Explanation:
Outriggers require formal authorization before use, and that approval must be in hand before any outriggers are set up. The CD-5 Outrigger permit is the official document that confirms the rigging plan, site conditions, and load calculations have been reviewed and approved for safe deployment. Having this permit on hand ensures all safety checks and coordination with the work environment have been completed, so the setup can proceed without hidden risks. Without the permit, setting up outriggers isn’t permitted. The other options imply no permit or a different, unrelated permit, which doesn’t meet the required safety procedure. So, the rule is: a CD-5 Outrigger permit must be on hand before outriggers can be set up.

Outriggers require formal authorization before use, and that approval must be in hand before any outriggers are set up. The CD-5 Outrigger permit is the official document that confirms the rigging plan, site conditions, and load calculations have been reviewed and approved for safe deployment. Having this permit on hand ensures all safety checks and coordination with the work environment have been completed, so the setup can proceed without hidden risks. Without the permit, setting up outriggers isn’t permitted. The other options imply no permit or a different, unrelated permit, which doesn’t meet the required safety procedure. So, the rule is: a CD-5 Outrigger permit must be on hand before outriggers can be set up.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy