If outriggers are to be set up, which statement about permits is correct?

Prepare for the Special Riggers Test. Study with flashcards and multiple-choice questions, complete with hints and explanations. Ace your exam!

Multiple Choice

If outriggers are to be set up, which statement about permits is correct?

Explanation:
Outriggers change how load is spread and how stable the setup will be, so their deployment must be authorized with a specific permit before they’re installed. The CD-5 Outrigger permit is the formal check that the site, conditions, and rigging plan have been reviewed and approved for this equipment. Having this permit on hand ensures you’re protected by the correct safety guidelines and that the setup follows the approved configuration, including base conditions and load limits. General construction permits don’t cover the specialized safety checks for outriggers, and proceeding without any permit isn’t compliant.

Outriggers change how load is spread and how stable the setup will be, so their deployment must be authorized with a specific permit before they’re installed. The CD-5 Outrigger permit is the formal check that the site, conditions, and rigging plan have been reviewed and approved for this equipment. Having this permit on hand ensures you’re protected by the correct safety guidelines and that the setup follows the approved configuration, including base conditions and load limits. General construction permits don’t cover the specialized safety checks for outriggers, and proceeding without any permit isn’t compliant.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy